| Ref
No |
Recommendation |
Action |
Responsible Agency/Lead Person |
Completion Date |
1 |
The Independent Chair of the LSCB should require the Teenage Pregnancy Strategy Coordinator to provide (by 30 November 2009) an overview of the current progress of the implementation of the Strategy, with particular reference to services for teenage fathers, age criteria, and to identify any gaps. The LSCB will then determine if further actions are necessary and formulate an action plan |
1) The LSCB to require the Teenage Pregnancy Strategy Coordinator to provide an overview report of the current progress of the implementation of the Strategy, with particular reference to services for teenage fathers, age criteria, and to identify any gaps.
2) The Policy and Procedure sub group to assess this return and to identify to the LSCB what actions are required and formulate action plan to address any shortfalls |
LSCB Manager
Chair Policy and Procedures Sub Group |
30 November 2009
1 April 2010 |
2 |
The Independent Chair of the LSCB should ensure (by 31 March 2010) that all agencies have an appropriate procedure and protocol governing the referral to Teenage Pregnancy Services of all cases when teenage females disclose they are pregnant or males disclose they are to become fathers. |
The Policy and Procedures sub group to require partner agencies to:
-
Review their procedures for referral to the Children Leeds Teenage Parent Care Pathway
-
Update / develop procedures in the light of (1)
|
Chair Policy and Procedure Sub Group |
31 December 2009
31 March 2010
|
3 |
The Independent Chair of the LSCB will ensure that all partner agencies involved in this Serious Case Review will (by 31 March 2010) undertake a review of the accuracy and detail of their agencies identification and recording of diversity. Where shortfalls are identified an action plan will be developed to implement required changes. |
The Performance Management sub group to require partner agencies to:
-
Undertake a review of their identification and recording of diversity
-
In the light of (1) initiate an improvement plan to implement identified changes
|
Chair Performance Management Sub Group |
31 December 2009
March 2010 |
4 |
The Independent Chair of the LSCB should ensure (by 31 March 2010) that the LSCB Support Team undertakes sample audits of the returns provided by partner agencies in respect of the information sharing component of Section 11/S157 & S175 and reports the outcomes to the LSCB. |
1)The LSCB Support Team to undertake a sample audit of the returns provided by partner agencies in respect of the information sharing component of Section 11/S157 & S175
2) The LSCB Support team to assess this audit and to identify to the Board what actions are required in order to address any shortfalls |
LSCB Manager
LSCB Manager
|
31 January 2010
31 March 2010
|
5 |
The Chief Executive of the Leeds Teaching Hospital Trust will remind Midwifery and Maternity staff in writing (by 31st December 2009) of the guidance and practice relating to the appropriate engagement of fathers in ante natal, birth and post natal services and appointments. |
- The Head of Midwifery will ensure all midwifery and maternity staff are made aware of the need to engage fathers in ante-natal, birth and post natal services
- Available written information around these issues will be cascaded to midwives
- Midwifery procedures must ensure that the rights of the mother are not over-ridden by such action
|
Head of Midwifery |
31 December 2009 |
6 |
The Chief Executive of NHS Leeds Community Healthcare should remind Health Visitors in writing (by 31 December 2009) of the need to ensure that:
(i) There is follow up discussion of leaflets provided.
(ii) Information is gathered in relation to health and welfare issues affecting the child which have occurred between visits and
(iii) Accommodation arrangements for the child/family are confirmed, assessed and reviewed. |
- written information covering (1),(11),(111) will be cascaded to Health Visiting Teams in the form of the weekly Bulletin
|
General Manager |
31 October 2009 |
7 |
The Chief Officer of the Integrated Youth Support Services should (by 31 March 2010) seek assurance that case work supervision and managerial oversight provided is of a sufficient standard to enable front-line staff to identify safeguarding issues even though the primary client is the young person/parent. |
The Integrated Youth Support Service Manager will undertake a review of Connexions providers in order to assure themselves that case work supervision and managerial oversight provided is of a sufficient standard to enable front-line staff to identify safeguarding issues even though the primary client is the young person/parent. |
Integrated Youth Support Service Manager |
31 March 2010 |
8 |
The Chief Officer of the Integrated Youth Support Services should (by 31 March 2010) ensure that the client information database has the capacity to identify (i) teenage parents and partners who are also known to the service and (ii) all clients of Connexions who live at the same address. |
The Integrated Youth Support Service Manager will assure themselves that the client information database has the capacity to identify (i) teenage parents and partners who are also known to the service and (ii) all clients of Connexions who live at the same address. |
Integrated Youth Support Service Manager |
31 March 2010 |
9 |
The Chief Housing Services Officer (Environment and Neighbourhood Services) should (by 31 December 2009) improve the standard of case file recording by completing the ongoing review of case file standards in the Homeless Service, identifying shortfalls and making necessary improvements. |
a. Review case file standards through sample of customer files
b. Establish expected standards for all files
c. Undertake training programme for all staff at the Leeds Housing Options Service
d. Undertake regular checks of case file management by senior staff within the service, identifying any shortfalls and work with individual officers to improve the standard of work
e. Ensure that the new computer system (Archouse Plus) currently under development reflects the expected standards. |
Head of Housing Strategy and Solutions, Leeds City Council |
- Completed end July 2009
- Completed end of July 2009
- Completed end of August 2009
- Quality Assurance Panels commenced mid-August 2009, ongoing, meet twice weekly
- Specification completed mid-October 2009 with new IT system live from mid-December 2009
|
10 |
The Governor of HMP, YOI, should review the roles and responsibilities of the Chaplaincy Service with regard to the information-sharing around safeguarding issues, including the provision of information to Serious Case Reviews. |
1) Undertake a review of protocol on information-sharing and safeguarding issues.
2) In the light of 1) initiate any changes. |
Deputy Governor Wetherby YOI |
Received July 2010 |